Installation of the gantry crane KC-50-42 was executed.

Friday, August 30, 2013State Regional Power Plant in Novocherkhassk Power Block # 9. Novocherkhassk.

Installation of gantry crane KC-50-42 with the load capacity 50 tons on the preparation area for the production was completed.

Works on gasket and rolling of the condenser's pipes were executed. Technical condition K-330-23,5.

Preparation works of rotor's winding up into startor of turbine generator TGV-330-2MUZ are being conducted.

Gantry crane KC-50-42Gantry crane KC-50-42