Delivery of the blocks flue in State Regional Electric Power Plant.

Friday, August 30, 2013Northern Production Section ( Production). Saint Petersburg.

We have begun work on compensation and preparations for the production of the blocks' flue for further delivery to the building of the Power Block №9 in Novocherkhasskaya State Regional Power Plant . Total volume of delivery will exceed 475 tons.

Date of redaction:12.09.2014 9:11:08